NASA reported KSC was preparing its facilities for next yr's Space Shuttle arrival and prelaunch work, more than 3yr after it last launched a Saturn rocket from Complex 39. In Oct. 1978, Shuttle Orbiter 102 would fly in from Calif. on its Boeing 747 carrier, with the main engines, external tank, and solid-fuel rocket boosters due in Nov. and Dec. for assembly and test before launch March 1979. KSC's orbiter landing strip had been completed in Aug.; support facilities to be completed by April 1978 would include a device to unload the orbiter, plus a microwave landing system to guide it to an automatic landing. An orbiter-processing facility to store fuels and handle payloads was the only new construction except the landing strip, the rest being modifications of Apollo facilities. (NASA Release 77-253)