Apr 24 1975
From The Space Library
NASA announced the award of a $2 376 400 contract to Reinhold Construction Co. for phase 2 of the Space Shuttle landing facility, including the landing aids control building, Orbiter landing instrumentation facilities, and related communications and utility systems. Phase 2 was scheduled for completion by the end of 1976.
Phase 1, which began in April 1974 as a $21 812 737 contract with Morrison Knudsen Co., included construction of the 4570-m-long, 91-m-wide runway, towway apron, and towway. Site preparation was nearing completion and the paving with nearly 200 000 cu m of cement would begin in July. Phase 1 was scheduled for completion by the summer of 1976. (KSC Release 62-75)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30